This framework is designed to help you create a data file that meets the Project Assessment and Reporting System (PARS) Comprehensive Project Performance (CPP) upload requirements as specified by DOE. It includes both a machine-readable format for software development and a human-readable PDF document approved for easy reference. It's important to note that while this schema checks for basic file integrity, the PARS application performs additional quality checks.
The JSON Schema is a blueprint for structuring cost, schedule, and other Earned Value Management System (EVMS) data for submission to PARS. Your JSON file must adhere to this schema to be accepted by PARS.
A proper PARS JSON file submission should be a zip file named after the PARS ID and the CPP status date (e.g., 1026_2023-07-28.zip). This zip file should contain JSON files that are named according to the DS number and title (like DS01_WBS.json, DS07_IMPR_header.json). It's crucial that the PARSID and CPP_status_date within each JSON file are consistent. If you have multiple zip files generated by different tools, the PARS uploader will accept and process multiple files so long as there is only one of each dataset.
Datasets DS01 through DS07 are required for a successful upload, and additional datasets will be required in the future. All datasets are currently accepted and contractors are encouraged to provide the most comprehensive upload possible.
The PARS Support Team oversees this schema and handles the technical aspects of PARS uploads. For any queries, reach out to them at support@pars.doe.gov.
No Additional PropertiesThe JSON schema for this object. This should always be set to the ID of this schema document.
PARS identifier for the project for which data is submitted. Should look like a 1-4 digit integer, but is a string.
Contractor data-as-of-date, align with DS22.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Use this field to store any labeling or designations related to data security such as CUI designations. Populate as appropriate to project's or site's security policies.
This data set should be populated with the project's contractor WBS identifiers for the
entire span of the project (not the contract).
Provide the contractor WBS identifiers in
a hierarchical structure from the project (not the contract) level to the CA WBS level and
to the WP and PP WBS levels.
The data set should include all WBS identifiers in all
other DSs in the same format. The data should align with dollarized RAM identifying
intersections of CA WBS and OBS types.
Must contain a
minimum of 1
items
This object represents a single WBS record for a project
No Additional PropertiesUnique contractor WBS identifier.
Must be at least 1
characters long
Must be at most 150
characters long
"W001.42.27.02"
Unique WBS identifier title.
Must be at least 1
characters long
Must be at most 255
characters long
"Testing/Surveillance Improvements"
WBS identifier hierarchical level relative to the project.
The
data is > 0, starting with 1 and increments by 1.
The dataset
should have only one level 1 WBS identifier that represents the
entire project.
Value must be greater or equal to
1
and lesser or equal to 20
WBS identifier of the immediate hierarchical parent.
Required
unless DS01.level = 1.
Must be at least
1
characters long
Must be at most
150
characters long
"1.42.27"
WBS type selection:
• WBS = summary level
• SLPP = summary
level planning package (assigned to project manager not to a CAM;
thus, is not a CA and does not have any WP, PP, or lower
DS01.WBS_level
• CA = control account
• PP = planning
package
• WP = work package
MR, UB, contingency, and SM
tasks should be associated with DS01.type = WBS.
Should be set
to PP or SLPP if DS03.EVT = K.
BCWS, BCWP, ACWP, and ETC are
roll-ups where DS01.type = CA or WBS.
BCWS, BCWP, ACWP, and ETC
are accounted for where DS01.type = WP or PP.
While not
preferred, ACWP may be collected at the CA level, i.e. where
DS01.type = CA. However, the level ACWP is collected must be uniform
across the dataset, i.e., all at CA or all at WP.
Unique contractor OBS identifier that should be aligned with the
associated CA and DS02.OBS.
If DS01.type is above the CA,
associate to the higher level OBS identifier.
Must be at least 1
characters long
Must be at most 50
characters long
"SC.CMCS.1.4.1"
CAM selection:
• CAM name for DS01.type = CA, WP, PP.
•
Project manager name for DS01.type = SLPP.
• Project or
appropriate manager name for DS01.type = WBS.
Format: [last
name] space [first name] space [middle initial, optional].
Must be at least 1
characters long
Must be at most 100
characters long
"Whitney Zachary B"
WP manager.
Required if DS01.type is WP or PP.
Format: [last
name] space [first name] space [middle initial, optional].
Must be at least 1
characters long
Must be at most 100
characters long
"Guitierez Jose"
Unique subproject identifier aligned with DS04.subproject_ID.
Required if DS01.WBS_external = Y.
Must be at least
1
characters long
Must be at most
50
characters long
Unique IMP identifier.
Must be at least 1
characters long
Must be at most 50
characters long
WBS is external to the project (Y or N).
Criteria to determine completion of the WBS scope.
Required if
DS01.type = CA or SLPP.
Provide if available for DS01.type =
WBS, WP, or PP.
Must be at least
1
characters long
Must be at most
3000
characters long
WBS identifier description from the EVMS cost tool; the scope
statement or a short paragraph based on the WBS dictionary and
aligned with DS08.narrative.
Align with DS08.narrative.
Must be at least 1
characters long
Must be at most 10000
characters long
"Testing/Surveillance Improvements"
Contractual basis: contract number, section(s), and paragraph(s).
Align with DS07.K_ID.
Must be at least 1
characters long
Must be at most 3000
characters long
Unique base work construct identifier.
Level 3 BWC where
DS01.type = SLPP, WP, or PP.
Level 2 and 3 BWC:
• W.01
support
• W.01.01 project
• W.01.02 closeout
•
W.01.03 operations
• W.02 engineering
• W.02.01
R&D
• W.02.02 conceptual
• W.02.03 preliminary
•
W.02.04 final
• W.02.05 general
• W.03 procurement
•
W.03.01 general
• W.04 construction
• W.04.01
engineering support
• W.04.02 demolition
• W.04.03 site
preparation
• W.04.04 construction
• W.05 SU-Cx
•
W.05.01 preparation
• W.05.02 SU
• W.05.03 cold cx
•
W.05.04 hot cx
Note: As of v5-0-2, values in this field are
not validated to exactly match with the options. It is anticipated
that in future versions, BWC_IDs will be required to contain the
code only, e.g., W.02.01.
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor functionally-based OBS
identifiers for the entire span of the project (not the contract).
Provide the
contractor OBS identifiers in a hierarchical structure from the project level to the CA WBS
level.
The data should include all OBS identifiers in all other DSs in the same format.
The data should align with dollarized RAM identifying intersections of CA WBS and OBS types.
Must contain a
minimum of 1
items
This object represents a single OBS record for a project
Unique contractor OBS identifier.
Must be at least 1
characters long
Must be at most 50
characters long
"MB.FC.4.2.82"
Unique OBS identifier title.
Must be at least 1
characters long
Must be at most 255
characters long
"Payroll & Benefits Accounting"
"Workforce Planning"
OBS identifier hierarchical level relative to the project.
The
data is > 0, starting with 1 and increments of 1.
The data
should have only one level 1 OBS identifier, the OBS identifier
representing the head of the contractor.
Value must be greater or equal to
1
and lesser or equal to 20
OBS identifier of the immediate hierarchical parent.
Required
unless DS02.level = 1.
Must be at least
1
characters long
Must be at most
50
characters long
"MB.FC.4.2.82"
OBS is external to the project (Y or N).
OBS identifier description from the EVMS cost tool.
A short
paragraph based on the functional OBS.
Align with
DS08.narrative.
Must be at least 1
characters long
Must be at most 3000
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor EVMS cost tool time-phased
data for the entire span of the project (not the contract).
Provide the contractor EVMS
cost tool time-phased data at the WP and PP WBS level by EOC.
The data should be
provided at the WP, PP, and SLPP WBS levels only with one period_date/WBS_ID_WP/EOC record;
however, provide at CA WBS level for only those CAs where ACWP (DS03.ACWPi_dollars and
DS03.ACWPi_units) is reported for entire project.
Must contain a
minimum of 1
items
This object represents a single cost record for a project
No Additional PropertiesTime-phased period end dates.
The data should align with the the
CPP_status_dates, and not change during the span of the project.
"2020-01-01"
Unique WBS Identifier when data is reported at WP or PP level. Omit
if data is not reported at WP or PP level.
• This should always
have a matching entry in DS01.WBS_ID where DS01.type = WP or PP.
Must be at least 1
characters long
Must be at most 150
characters long
"1.42.27.2"
Unique WBS Identifier for the Control Account:
• If data is
reported at the CA level, populate with the CA WBS_ID where data is
reported.
• If data is reported at the WP or PP level, populate
with the WBS_ID of the Control Account associated with the WP or
PP.
• This should always have a matching entry in DS01.WBS_ID
where DS01.type = CA.
Must be at least 1
characters long
Must be at most 150
characters long
"1.42.27.2"
EOC selection:
• labor
• material
• subcontract
•
ODC
• indirect (may be used after coordination with PM. To
consist only of indirect costs.)
EVT selection that should be aligned with DS04.EVT (provide
explanations in DS03.justification_EVT):
• A = LOE
• B =
weighted milestones (explain if utilized)
• C = percent complete
or for use in DS03, discrete (combination of discrete DS03.EVT
excluding A, J, K, M, or NA)
• D = units complete
• E =
50-50
• F = 0-100
• G = 100-0 (explain if utilized)
• H
= variation of 50-50 (explain if utilized)
• J = apportioned
(explain if utilized)
• K = planning package (overrides where
DS01.type = PP or SLPP)
• L = assignment percent complete
(explain if utilized)
• M = calculated apportionment (explain if
utilized)
• N = steps (explain if utilized)
• O = earned as
spent (explain if utilized)
• P = percent manual entry (explain
if utilized)
• NA = only for DS01.type = CA where ACWP is
reported for the entire project.
Discrete EVTs for metrics
consists of B, C, D, E, F, G, H, L, N, O, P.
Required if
DS01.type = WP, PP, or SLPP.
Justification narrative where DS03.EVT = B, G, H, J, L, M, N, O, or P.
DS03.WBS_ID_WP apportioned to, if DS03.EVT = J or M.
Percent apportioned, if apportioned from another DS03.WBS_ID_WP.
BCWS incremental (dollars).
11234.09
355651.29
BCWP incremental (dollars).
11234.09
355651.29
ACWP incremental (dollars).
11234.09
355651.29
ETC incremental (dollars).
11234.09
355651.29
Represents indirect costs only (Y or N)?
N if record is direct
costs only.
Omit this field if costs include both direct and
indirect costs.
BCWS incremental (hours) where DS03.EOC = labor only.
128.6
45.3
80.75
BCWP incremental (hours) where DS03.EOC = labor only.
128.6
45.3
80.75
ACWP incremental (hours) where DS03.EOC = labor only.
128.6
45.3
80.75
ETC incremental (hours) where DS03.EOC = labor only.
128.6
45.3
80.75
BCWS incremental (FTE) where DS03.EOC = labor only.
BCWP incremental (FTE) where DS03.EOC = labor only.
ACWP incremental (FTE) where DS03.EOC = labor only.
ETC incremental (FTE) where DS03.EOC = labor only.
Reprogramming CV. Reprogramming adjustment, cost variance.
Reprogramming SV. Reprogramming adjustment, schedule variance.
Reprogramming BAC. Reprogramming adjustment, DB variance.
Charge code identifier.
Must be at least 1
characters long
Must be at most 50
characters long
"MB.FC.4.2.82"
"MB.WC.1.4.1"
"MB.WC.1.8.1"
"SC.CMCS.1.4.1"
Charge code description.
Must be at least
1
characters long
Must be at most
3000
characters long
"Payroll & Benefits Accounting"
"Workforce Planning"
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor BL and FC IMS tool data for
the entire span of the project (not the contract).
Provide the contractor BL and FC IMS
tool data by task.
There should be alignment between the BL and FC IMSs.
Must contain a
minimum of 1
items
This object represents a single schedule record for a project
No Additional PropertiesSchedule type selection:
• BL = baseline
• FC = forecast
The data should be scheduled by the schedule tool.
Task identifier.
Must be at least 1
characters long
Must be at most 50
characters long
"AHBL1190"
"TASK-1"
"TASK-2"
"TASK-3"
Task type selection:
• TD = task dependent. Task is scheduled
using its task calendar.
• RD = resource dependent. Task is
scheduled using its resource calendar(s).
• LOE = level of
effort. Task duration by its dependent task. Used for administration
type tasks. Use should be limited. Likely DS04.EVT = A (level of
effort) but could be different. Should have a start-to-start and a
finish-to-finish predecessor relationship to a discrete
tasks(s).
• SM = start milestone. Tasks with 0 duration and no
resources.
• FM = finish milestone. Task with 0 duration and no
resources.
• WS = WBS summary. Task of aggregated tasks with
common DS04.WBS_ID. Use should be limited.
Unique task description.
Should be descriptive with a verb.
Must be at least 1
characters long
Must be at most 255
characters long
Task subtype selection:
• SVT = A non-PMB task for
visibility/functionality to characterize potential impacts to the
logic-driven network. Generally based on another project as a
predecessor with a finish-to-start relationship. Generally
constrained based on programmatic schedule with DS04.constraint_type
= CS.MSOA or DS04.constraint_type = CS.MEOA but may be a hard
constraint; DS04.constraint_type = M; not resource loaded.
• ZBA
= zero budget activity. For subK payment tasks. Used on a limited
basis; not resource loaded. Align with DS04.milestone_level = 8xx.
Milestone level selection for tasks that identify key milestones,
deliverables, and control point dates (DS04.type = SM or FM).
Milestone level should align with DS04.constraint_type as
appropriate.
• 1xx = DOE O 413.3B milestones. All 1xx are
considered DS04.task_subtype = SVT, unless otherwise noted. Required
milestones: All DOE Order 413.3B milestones and milestones 100, 175,
180, 190, 195, 199.
• 100 = approve start project
• 110
= approve CD-0
• 111 = approve CD-0R-01
• 112 = approve
CD-0R-02
• 120 = approve CD-1
• 121 = approve
CD-1R-01
• 122 = approve CD-1R-02
• 130 = approve
CD-2
• 131 = approve BCP-01
• 132 = approve BCP-02
• 133 = approve BCP-03
• 134 = approve BCP-04
• 135 =
approve BCP-05
• 138 = approve reprogramming (not SVT)
(Specify if OTB and/or OTS in DS04.milestone_level_description)
• 139 = approve replan (not SVT)
• 140 = approve CD-3A
• 141 = approve CD-3B
• 142 = approve CD-3C
• 143 =
approve CD-3D
• 144 = approve CD-3E
• 145 = approve
CD-3F
• 150 = approve CD-3
• 160 = approve CD-4A
•
161 = approve CD-4B
• 162 = approve CD-4C
• 163 =
approve CD-4D
• 164 = approve CD-4E
• 165 = approve
CD-4F
• 170 = planned/estimated completion without UB
•
175 = End of PMB. Planned/estimated completion with UB (calculated
schedule reserve should align with duration from
DS04.milestone_level = 175 to DS04.milestone_level = 180; should be
aligned with DS03 last BCWS for BL or last ETC for FC to achieve
CD-4; this is the end of the PARS ID; not SVT)
• 180 =
contract completion (calculated schedule contingency should align
with duration from DS04.milestone_level = 180 to
DS04.milestone_level = 190) (Should be aligned with CBB date for BL
or est CBB date for FC) (not SVT)
• 190 = approve CD-4
•
195 = approve closeout
• 199 = approve finish project
•
2xx = contract driven milestones & periods of performance
•
3xx = customer driven milestones. All 3xx are considered
DS04.task_subtype = SVT.
• 4xx = programmatic driven
milestones
• 5xx = major internal driven milestones
• 6xx =
minor internal driven milestones
• 7xx = external driven
milestones, e.g., regulatory, consent decree. All 7xx are considered
DS04.task_subtype = SVT.
• 8xx = subK alignment milestones;
align with DS13.task.
Value must be greater or equal
to 100
and lesser or equal to 999
100
110
195
Milestone level description.
Should align with
DS04.milestone_level.
Should be descriptive with a verb.
Must be at least
1
characters long
Must be at most
50
characters long
WP or PP or SLPP WBS identifier. Explain in DS04.justification_WBS if DS01.type is not WP, PP or SLPP.
Must be at least 1
characters long
Must be at most 150
characters long
Justification narrative for WBS identifier is not WP or PP or SLPP
WBS.
Not required if no justification narrative for WBS
identifier is not WP or PP or SLPP WBS.
CAM selection:
• CAM name for DS01.type = CA, WP, PP.
•
Project manager name for DS01.type = SLPP.
• Project or
appropriate manager name for DS01.type = WBS
Format: [last name]
space [first name] space [middle initial, optional].
Should
align with DS01.CAM.
Must be at least 1
characters long
Must be at most 100
characters long
"Whitney Zachary B"
"Burks Deanna A"
"Simon Avaya S"
"Moses Kendall"
EVT selection that should be aligned with DS03.EVT (explanations
should go in DS04.justification_EVT):
• A = LOE. Should have a
start-to-start and a finish-to-finish predecessor relationship to a
discrete task(s).
• B = weighted milestones (explain if
utilized)
• C = percent complete or for use in DS03, discrete
(combination of discrete DS03.EVT excluding A, J, K, M, or NA)
•
D = units complete
• E = 50-50
• F = 0-100
• G = 100-0
(explain if utilized)
• H = variation of 50-50 (explain if
utilized)
• J = apportioned (explain if utilized). Should have a
start-to-start and a finish-to-finish predecessor relationship to a
discrete task(s).
• K = planning package (overrides where
DS01.type = PP or SLPP)
• L = assignment percent complete
(explain if utilized)
• M = calculated apportionment (explain if
utilized). Should have a start-to-start and a finish-to-finish
predecessor relationship to a discrete task(s).
• N = steps
(explain if utilized)
• O = earned as spent (explain if
utilized)
• P = percent manual entry (explain if utilized)
Discrete EVTs for metrics consists of B, C, D, E, F, G, H, L, N, O,
P.
Justification narrative where DS04.EVT = B, G, H, J, L, M, N, O, or P.
task_ID apportioned to, if DS04.EVT = J.
Percent apportioned, if apportioned from another DS04.task_ID.
Early start date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Early finish date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Late start date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Late finish date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Actual start date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Actual finish date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Original duration (work days).
Remaining duration (work days).
Actual duration (work days).
Free float (work days).
Total float (work days).
Justification narrative for high float, DS04.float_total_days.
Justification narrative for lag relation with predecessor, DS05.lag_days <> 0.
Task is on the longest path or on the driving path (Y or N).
Align with only one DS15.risk_ID.
Provide if an RMT.
Must be at least 1
characters long
Must be at most 255
characters long
% complete type selection (% complete used to calculate BCWP):
•
duration (utilized when DS04.type = LOE or DS04.EVT = A)
•
physical (utilized when DS04.type <> LOE, and DS04.EVT
<> A)
• units (utilized when DS06.EOC = material)
Duration % complete.
If % complete = 100%, 1.00.
If 99% <=
% complete < 100%, 0.99 (truncate remainder).
If 0 < %
complete < 99%, round to 2 digits.
If 0 = % complete, 0.00.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple
of 0.01
Physical % complete.
If % complete = 100%, 1.00.
If 99% <=
% complete < 100%, 0.99 (truncate remainder).
If 0 < %
complete < 99%, round to 2 digits.
If 0 = % complete,
0.00.
Utilize if DS04.type = TD or RD.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple
of 0.01
Units % complete.
If % complete = 100%, 1.00.
If 99% <= %
complete < 100%, 0.99 (truncate remainder).
If 0 < %
complete < 99%, round to 2 digits.
If 0 = % complete,
0.00.
Utilize if DS04.type = TD or RD and DS06.EOC = material.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple
of 0.01
Start primary constraint type selection:
• CS_ASAP = as soon as
possible (not considered a soft or hard constraint)
•
CS_MANDSTART = mandatory start (considered hard constraint)
•
CS_MSO = must start on (considered hard constraint)
• CS_MSOA =
must start on or after (considered soft constraint)
• CS_MSOB =
must start on or before (considered hard constraint)
Finish
primary constraint type selection:
• CS_ALAP = as late as
possible (not considered a soft or hard constraint)
• CS_MANDFIN
= mandatory finish (considered hard constraint)
• CS_MEO = must
finish on (considered hard constraint)
• CS_MEOA = must finish
on or after (considered soft constraint)
• CS_MEOB = must finish
on or before (considered hard constraint)
Provide hard
constraint justification in DS04.justification_constraint_hard.
Provide soft constraint justification in
DS04.justification_constraint_soft.
Identify secondary
constraint in DS04.justification_constraint_secondary.
Primary constraint date.
Not required if DS04.constraint_type =
CS_ALAP or not provided.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Justification narrative for hard constraint, DS04.constraint_type.
Justification narrative for soft constraint, DS04.constraint_type.
Description and justification narrative for secondary start and finish constraints.
HDV-CI identifier.
The data should align with DS14.HDV_CI_ID.
Must be at least 1
characters long
Must be at most 50
characters long
Task is for a reprogramming effort.
Calendar name for task.
Align with DS19.calendar_name and
DS20.calendar_name.
Required unless task is an SVT.
Must be at least
1
characters long
Must be at most
1000
characters long
Unique subproject identifier.
Tasks not in project scope should
be associated with that task's primary project, not this project's
primary project. This includes SVTs, tasks pre-CD-0, and tasks post
DS04.milestone_level = 175.
Must be at least
1
characters long
Must be at most
100
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor BL and FC IMS tool task relationship data for the DS04 tasks. The contractor BL and FC IMS tool task relationship data by task and predecessor. There should be alignment between the BL and FC IMSs.
Must contain a
minimum of 1
items
This object represents a single schedule resource record for a project
No Additional PropertiesSchedule type selection:
• BL = baseline
• FC = forecast
The data should be scheduled by the schedule tool.
Unique task identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Task identifier of the predecessor task.
The data should align
with DS04.task_ID.
Must be at least
1
characters long
Must be at most
50
characters long
Task relationship (task to its predecessor) selection:
• FS =
finish to start
• SS = start to start
• SF = start to
finish
• FF = finish to finish
Task relationship lag (work days) based on predecessor's
calendar.
The data is positive if lag.
The data is negative
if lead.
Unique subproject identifier.
Must be at least
1
characters long
Must be at most
100
characters long
Subproject identifier of the predecessor task's subproject, if applicable.
Must be at least
1
characters long
Must be at most
100
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor BL and FC IMS tool task role
and resource data for the DS04 tasks.
Provide the contractor BL and FC IMS tool task
role and/or resource data by task.
There should be alignment between the BL and FC IMSs.
Must contain a
minimum of 1
items
This object represents a single schedule resource record for a project
No Additional PropertiesSchedule type selection:
• BL = baseline
• FC = forecast
The data should be scheduled by the schedule tool.
Unique task identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Unique resource identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Unique resource name.
Must be at least
1
characters long
Must be at most
100
characters long
Unique role identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Unique role name.
Must be at least 1
characters long
Must be at most 100
characters long
Resource type selection:
• labor where DS06.EOC = labor
•
nonlabor where DS06.EOC is not labor
• material where DS06.EOC
is not labor
EOC selection:
• labor
• material
• subcontract
•
ODC
• indirect (may be used after coordination with PM. To
consist only of indirect costs).
Resource start date.
For FC IMS, updated resource start or
started date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Resource finish date.
For FC IMS, updated resource finish or
finished date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Total budget (dollars) aligned with BCWS.
Total actual (dollars) aligned with BCWP.
Total remaining (dollars) aligned with ETC.
Total budget (units) aligned with BCWS.
Units of measure are
specified in UOM field.
Total actual (units) aligned with BCWP.
Units of measure are
specified in UOM field.
Note: This represents BCWP, not ACWP.
Total remaining (units) aligned with ETC.
Units of measure are
specified in UOM field.
Unit of measure.
If resource_type is labor or non-labor, it is
h.
If it is material it is a string.
Must be at least 1
characters long
Must be at most 20
characters long
"h"
"CY"
"LF"
"tons"
Task relationship remaining lag (work days) based on predecessor's
calendar.
The data is positive if lag.
The data is negative
if lead.
Task relationship planned lag (work days) based on predecessor's
calendar.
The data is positive if lag.
The data is negative
if lead.
Unique subproject identifier.
Must be at least
1
characters long
Must be at most
50
characters long
Calendar name for resource.
Align with DS19.calendar_name and
DS20.calender_name.
Must be at least
1
characters long
Must be at most
1000
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This object should be populated with the project's contractor IPMR header data aligned with DS01 to DS06 and DS09 to DS12. Provide the contractor EVMS cost tool IPMR header data. This object contains IPMR header information so does not have an array of objects like other DS objects.
No Additional PropertiesUnique DOE contract number and, if applicable, CLIN(s).
Must be at least 1
characters
long
Must be at most 255
characters
long
Contract type selection:
• FFP = firm fixed price
• FPE = fixed price
escalation
• FPI = fixed price incentive
• CPIF = cost plus
incentive fee
• CPAF = cost plus award fee
• CPDS = cost plus fixed
fee
• CPE = cost plus expenses
• CPP = cost plus percentage
UB, budget applicable to the contract effort not yet distributed to the WBS identifiers at or below the reporting level (work days).
EAC for scope of work represented by the UB (work days).
UB, budget applicable to the contract effort not yet distributed to the WBS identifiers at or below the reporting level.
EAC for scope of work represented by the UB.
MR excluding OTB and OTS.
MR reprogramming adjustment factoring OTB and OTS.
AUW of the authorized, unpriced work for approved work scope that has not been definitized by the contracting officer. Amount is the procuring contracting officer's best estimate. Excludes fee and profit. AUW cannot be negative. For effort de-scoped and not yet reflected in the CBB.
Value must be greater or equal to 0
and a multiple of 0.01
NCC on which project was reached as of the reflected reporting period. Excludes fee and profit. For an incentive contract, the definitized contract target cost. For a cost plus fixed fee or award fee contract, the estimated negotiated cost that consists only of the estimates amount for changes in the contract scope of work and not for cost change (overrun or underrun) from the original cost. Amount for changes shall not be included until definitized in the contract.
CBB, the NCC plus AUW.
Date last OTB or OTS was approved by DOE and implemented.
Not required if
no OTB or OTS.
"2020-01-01"
"2019-02-26"
"2020-10-14"
TAB, total budget value allocated to the performance of the contractual
effort including MR and UB.
Excludes fee and profit.
Target profit or fee that applies to the negotiated contract cost.
Contractor's best case EAC for the contract cost for all authorized
contractual efforts.
Excludes fee and profit.
Contractor's most likely case EAC for the contract cost for all authorized
contractual efforts.
Excludes fee and profit.
Contractor's worst case EAC for the contract cost for all authorized
contractual efforts.
Excludes fee and profit.
Contractor's best case EAC date for all authorized contractual efforts.
Contractor's most likely case EAC date for all authorized contractual efforts.
Contractor's worst case EAC date for all authorized contractual efforts.
Escalation rate for DS07.TAB.
Quantitative risk analysis confidence level for cost DS07.MR_rpg and DS07.MR_bgt.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple of
0.01
Quantitative risk analysis confidence level for schedule and aligned with DS07.MR_rpg and DS07.MR_bgt.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple of
0.01
Project cost threshold (dollar) for cumulative variance analysis at CA WBS level, favorable.
Project cost threshold (dollar) for cumulative variance analysis at CA WBS level, unfavorable.
Project cost threshold (percent) for cumulative variance analysis CA WBS level, favorable.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple of
0.01
Project cost threshold (percent) for cumulative variance analysis CA WBS level, unfavorable.
Value must be greater or equal
to 0
and lesser or equal to 1
and a multiple of
0.01
Project cost threshold (dollar) for incremental variance analysis CA WBS level, favorable.
Project cost threshold (dollar) for incremental variance analysis CA WBS level, unfavorable.
Project cost threshold (percent) for incremental variance analysis CA WBS level, favorable.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple of
0.01
Project cost threshold (percent) for incremental variance analysis CA WBS level, unfavorable.
Value must be greater or equal
to 0
and lesser or equal to 1
and a multiple of
0.01
Project cost threshold (dollar) for VAC at project level, favorable.
Project cost threshold (dollar) for VAC at project level, unfavorable.
Project cost threshold (percent) for VAC at project level, favorable.
Value must be greater or equal to
0
and lesser or equal to 1
and a multiple of
0.01
Project cost threshold (percent) for VAC at project level, unfavorable.
Value must be greater or equal
to 0
and lesser or equal to 1
and a multiple of
0.01
Project schedule threshold (dollar) for cumulative variance analysis at CA WBS level, favorable.
Project schedule threshold (dollar) for cumulative variance analysis at CA WBS level, unfavorable.
Project schedule threshold (percent) for cumulative variance analysis CA WBS level, favorable.
Value must be greater or equal
to 0
and lesser or equal to 1
and a multiple of
0.01
Project schedule threshold (percent) for cumulative variance analysis CA WBS level, unfavorable.
Value must be greater or
equal to 0
and lesser or equal to 1
and a multiple
of 0.01
Project schedule threshold (dollar) for incremental variance analysis CA WBS level, favorable.
Project schedule threshold (dollar) for incremental variance analysis CA WBS level, unfavorable.
Project schedule threshold (percent) for incremental variance analysis CA WBS level, favorable.
Value must be greater or equal
to 0
and lesser or equal to 1
and a multiple of
0.01
Project schedule threshold (percent) for incremental variance analysis CA WBS level, unfavorable.
Value must be greater or
equal to 0
and lesser or equal to 1
and a multiple
of 0.01
Represents whether actual costs are collected at the control account level. If both DS03.ACWPi_dollars and DS03.ACWPi_hours for entire project are reported at DS01.type = CA then Y; otherwise, N for DS03.ACWPi_dollars and DS03.ACWPi_hours for entire project are reported at DS01.type = WP or PP
For use only for debugging and testing with the PARS support team. This field
should be omitted in production data.
The field should consist of a
comma separated list of unique DIQ identifiers that this row of data is
expected to trigger.
This data set should be populated with the approved project's contractor WAD data for the
entire span of the project (not the contract) to include from initial and all revisions.
The contractor WAD data by CA and SLPP WBS level and optional by PP and WP WBS levels.
Must contain a
minimum of 1
items
This object represents a WAD record for a project
No Additional PropertiesUnique WAD identifier.
Must be at least 1
characters long
Must be at most 50
characters long
WAD version.
Must be at least 1
characters long
Must be at most 50
characters long
WAD title.
Must be at least 1
characters long
Must be at most 255
characters long
CA or SLPP WBS identifier.
Must be at least 1
characters long
Must be at most 150
characters long
WP or PP WBS identifier.
Date WAD was last signed by contractor project manager.
Must be at least 1
characters long
Must be at most
255
characters long
Date WAD was last signed by CAM.
Must be at least
1
characters long
Must be at most
255
characters long
Date WAD was last signed by WPM.
Must be at least
1
characters long
Must be at most
255
characters long
Date WAD was initially signed by contractor project manager.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Provide if WBS_ID_WP is provided.
EVT selection that should be
aligned with DS03.EVT and DS04.EVT:
• A = LOE
• B = weighted
milestones
• C = percent complete or for use in DS03,
discrete
• D = units complete
• E = 50-50
• F =
0-100
• G = 100-0
• H = variation of 50-50
• J =
apportioned
• K = planning package (overrides where DS01.type =
PP or SLPP)
• L = assignment percent complete
• M =
calculated apportionment
• N = steps
• O = earned as
spent
• P = percent manual entry
Discrete EVTs for metrics
consists of B, C, D, E, F, G, H, L, N, O, P.
Total budget for EOC labor (dollars).
Total budget for EOC material (dollars).
Total budget for EOC subcontract (dollars).
Total budget for EOC ODC (dollars).
Total budget for EOC indirect (dollars).
Total labor budget (hours).
WBS POP start date, as defined by the latest approved baseline
change.
Not required if DS10.transaction_ID is not DB.
"2020-01-01"
"2019-02-26"
"2020-10-14"
WBS POP finish date, as defined by the latest approved baseline
change.
Not required if DS10.transaction_ID is not DB.
"2020-01-01"
"2019-02-26"
"2020-10-14"
CAM who signed WAD.
Format: [last name] space [first name] space
[middle initial, optional]
Must be at least 1
characters long
Must be at most 100
characters long
PP or WP WBS level manager.
Optional if DS01.type = PP or WP.
Format: [last name] space [first name] space [middle initial,
optional]
Must be at least 1
characters long
Must be at most 100
characters long
Contractor project manager.
Format: [last name] space [first
name] space [middle initial, optional]
Must be at least 1
characters long
Must be at most 100
characters long
CA WBS scope statement (not title) encompassing all scope per WAD and aligned with DS01.narrative and DS02.narrative.
Must be at least 1
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor project change control log
data for the entire span of the project (not the contract).
Provide the contractor
approved project change control log data by CC_log identifier.
The data should include
the initial CC_log and the initial deposit at the start of the project.
Must contain a
minimum of 1
items
This object represents a CC log record for a project
No Additional PropertiesCC identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Supplemental CC_log_ID, e.g. revisions.
Must be at least
1
characters long
Must be at most
50
characters long
For CCs that are approving distribution of budget from UB, this should have original CC_log_ID that approved increase of UB account through AUW or modification.
Must be at least
1
characters long
Must be at most
50
characters long
Change type selection (per DOE
Project Management Lexicon of Terms):
• Funding
•
BCP
• BCR
Provide when CC_log_ID is associated with a contract mod.
Scope description. (Do not include unapproved changes)
Must be at least 1
characters long
Approved date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Date during which the change has been implemented within contractor systems.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Total increase or decrease in budgeted dollars authorized by the change request. Represents the summation of the transactions detailed in DS10 CC_log_detail.
Total increase or decrease in budgeted number of hours authorized by the change request. Represents the summation of the transactions detailed in DS10 CC_log_detail.
Contractor project manager.
Format: [last name] space [first
name] space [middle initial, optional]
Must be at least 1
characters long
Must be at most 100
characters long
List of risk_IDs addressed by CC_log_ID.
Aligns with
DS15.risk_ID.
If multiple identifiers, separate with semicolons.
Must be at least 1
characters long
Must be at most 255
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor project change control log transaction data for DS09. Provide the contractor approved project change control log transaction data by CC_log identifier. The data should consist of CC_logs, each resulting in zero-sum of dollars that are moved between the transaction categories, unless new budget is added to the CBB.
Must contain a
minimum of 1
items
This object represents a CC log detail record for a project.
No Additional PropertiesUnique transaction identifier.
Must be at least
1
characters long
Must be at most
50
characters long
Transaction category selection:
• CNT = DOE contingency
• DB
= distributed budget (should also be identified by the CA WBS)
•
UB = undistributed budget account
• MR = management reserve
account
• OTB = over-target baseline only
• OTS =
over-target schedule only
• OTB-OTS = OTB and OTS
•
funding
• profit-fee
CC identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Transaction summary information.
Must be at least 1
characters long
WBS identifier.
Project level required for UB, MR, CNT.
CA or
lower level required if transaction type is DB.
Must be at least 1
characters long
Must be at most 150
characters long
CC_log impact (dollars) that changes the balance.
Value must be greater or equal to
0
and a multiple of 0.01
CC_log impact (hours) that changes the balance.
Value must be greater or equal to
0
and a multiple of 0.01
Transaction is for AUW.
NTE for DS10.AUW.
CA or WP WBS POP start date, only if modified.
"2020-01-01"
"2019-02-26"
"2020-10-14"
CA or WP WBS POP finish date, only if modified.
"2020-01-01"
"2019-02-26"
"2020-10-14"
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor variance data. Provide the contractor variance data by WBS identifier; for project, use the project level WBS identifier.
Must contain a
minimum of 1
items
This object represents a variance record for a project
No Additional PropertiesWBS identifier.
Must be at least 1
characters long
Must be at most 150
characters long
Narrative type selection:
• 100 PRJ = project level summary
•
110 RPG = project level formal reprogramming analysis
• 120 VAC
= project level VAC analysis
• 130 EAC = project level EAC
analysis
• 140 UB = project level UB analysis
• 150 MR =
project level MR analysis
• 160 IMS = project level IMS
discussion
• 170 F3 = project level IPMR F3 discussion
• 180
F4 = project level IPMR F4 discussion
• 200 SLPP = summary level
planning package (The data should not have SV or CV.)
• 300 CA =
control account
• 400 PP = planning package (The data should not
have SV or CV.)
• 500 WP = work package
Overall narrative.
Provide if DS11.narrative_type <200
Must be at least
1
characters long
Root cause narrative for incremental schedule variance.
Must be at least
1
characters long
Root cause narrative for incremental cost variance.
Must be at least
1
characters long
Root cause narrative for cumulative schedule variance.
Must be at least
1
characters long
Root cause narrative for cumulative cost variance.
Must be at least
1
characters long
Impact narrative for technical variance.
Must be at least
1
characters long
Impact narrative for cumulative schedule variance.
If
DS11.narrative_impact_schedule_inc is not utilized, provide combined
cumulative and incremental narrative for schedule variance.
Must be at least
1
characters long
Impact narrative for cumulative cost variance.
If
DS11.narrative_impact_cost_inc is not utilized, provide combined
cumulative and incremental narrative for cost variance.
Must be at least
1
characters long
Impact narrative for incremental schedule variance.
Must be at
least 1
characters long
Impact narrative for incremental cost variance.
Must be at least
1
characters long
Unique corrective action log identifier(s).
If multiple
identifiers, separate with semicolons.
Must be at least 1
characters long
Approved date by CAM.
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor corrective action data for
DS11.
Provide the contractor corrective action data by corrective action identifier.
The data should validate that corrective actions for variances are addressed, monitored, and
mitigated.
The data may be limited to the corrective actions that are open or closed
within the current reporting period, based on coordination with DOE.
Must contain a
minimum of 1
items
This object represents a variance CAL record for a project
No Additional PropertiesCorrective action log identifier.
Must be at least 1
characters long
Unique transaction identifier.
Must be at least
1
characters long
Must be at most
50
characters long
Corrective action narrative for cumulative schedule variance.
Must be at least
1
characters long
Corrective action narrative for cumulative cost variance.
Must be at least
1
characters long
Name of the person responsible for closing corrective action.
Does not have to be the same as CAM.
Format: [last name] space
[first name] space [middle initial, optional].
Must be at least 1
characters long
Must be at most 100
characters long
Current status of corrective action Item as it exists in contractor
log.
• open
• closed
Date of the initial corrective action.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Original due date by which corrective action was supposed to be closed.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Forecast due date that indicates expected closure date for the corrective action. DS12.closed_date if closed.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Actual date when corrective action was closed.
"2020-01-01"
"2019-02-26"
"2020-10-14"
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's subcontract work data as reported by the
subcontractors to the contractor.
The data should include all subcontracts that have
discrete work and that have schedule or cost reporting requirements.
The data should be
updated as subcontracts are negotiated.
The data may be limited to a single line per
subcontract due to type or size of the subcontract or data availability, based on
coordination with DOE.
Must contain a
minimum of 1
items
This object represents a subcontract work data record for a project
No Additional PropertiesUnique subcontract identifier (e.g., subcontract name).
Must be at least 1
characters long
Must be at most 50
characters long
Unique task ID from subcontract schedule.
Must be at least 1
characters long
Must be at most 50
characters long
DS04.task_ID associated with subcontract work.
Must be at least 1
characters long
Must be at most 50
characters long
BCWS cumulative (dollars).
BCWP cumulative (dollars).
ACWP cumulative (dollars).
DB (dollars).
BAC initial (dollars).
EAC (dollars).
Baseline start date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Baseline finish date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Forecast start date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Forecast finish date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Actual start date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Actual finish date.
"2020-01-01"
"2019-02-26"
"2020-10-14"
MR remaining (dollars).
MR initial (dollars).
Profit fee remaining (dollars).
Profit fee earned (dollars).
Profit fee initial (dollars).
Purchase order identifier.
DOE Order 413.3B CRD flow down required.
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor HDV-CI data. Provide the contractor HDV-CI data by WBS and HDV-CI identifiers.
Must contain a
minimum of 1
items
This object represents a HDV-CI record for a project
No Additional PropertiesUnique HDV-CI identifier. This data should align with DS04.HDV_CI_ID.
Must be at least 1
characters long
Must be at most 50
characters long
HDV-CI description.
Subcontract identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Purchase order identifier.
Must be at least 1
characters long
Must be at most 50
characters long
Equipment identifier.
Must be at least 1
characters long
Must be at most 50
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor risk log for the entire span of the project (not the contract). Provide the contractor risk log by risk identifier. The data should be updated through the CPP_status_date.
Must contain a
minimum of 1
items
This object represents a risk register record for a project
No Additional PropertiesUnique risk identifier.
Must be at least 1
characters long
Must be at most 255
characters long
Current revision number for the DS15.risk_ID
Must be at least 1
characters long
Must be at most 50
characters long
Risk description.
Format: if then.
Must be at least 1
characters long
Must be at most 500
characters long
Risk type selection:
• T = threat
• O = opportunity
Risk manager.
Format: [last name] space [first name] space
[middle initial, optional].
Must be at least 1
characters long
Must be at most 100
characters long
Risk owner selection:
• federal
• contractor
Approved date with risk handling selection.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Date risk realized.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Risk closed date when risk is no longer actively tracked but remains on the risk log.
"2020-01-01"
"2019-02-26"
"2020-10-14"
Risk event probability schedule min. (percent).
Value must be
greater or equal to 0
and lesser or equal to
1
and a multiple of 0.01
Risk event probability schedule max. (percent).
Value must be
greater or equal to 0
and lesser or equal to
1
and a multiple of 0.01
Risk event probability cost min. (percent).
Value must be greater
or equal to 0
and lesser or equal to 1
and
a multiple of 0.01
Risk event probability cost max. (percent).
Value must be greater
or equal to 0
and lesser or equal to 1
and
a multiple of 0.01
Risk handling selections:
• avoid
• mitigate
•
transfer
• accept
Notes.
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor risk log tasks for the entire
span of the project (not the contract).
Provide the contractor risk log tasks by risk
identifier.
The data should be updated through the CPP_status_date.
Must contain a
minimum of 1
items
This object represents a risk register tasks record for a project
No Additional PropertiesRisk identifier.
Align with DS15.risk_ID.
Must be at least 1
characters long
Must be at most 255
characters long
Risk task type selections:
• event (risk trigger, when risk is
relevant. If no event task for a risk_ID, then assume risk is
relevant for the entire project.)
• impact
Must be at least
1
characters long
Must be at most
50
characters long
Event or impact task identifier.
Aligned with DS04.task_ID and
based on DS16.risk_task_type.
Must be at least 1
characters long
Must be at most 50
characters long
Provide if DS16.risk_task_type = impact, schedule impact (calendar days) min.
Provide if DS16.risk_task_type = impact, schedule impact (calendar days) most likely.
Provide if DS16.risk_task_type = impact, schedule impact (calendar days) max.
Provide if DS16.risk_task_type = impact, cost impact (dollars) min.
Provide if DS16.risk_task_type = impact, cost impact (dollars) most likely.
Provide if DS16.risk_task_type = impact, cost impact (dollars) max.
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor WBS EU data for each DS01.WBS and basis documented. Provide the contractor WBS EU data.
Must contain a
minimum of 1
items
This object represents a forward pricing record for a project
No Additional PropertiesUnique contractor WP or PP WBS identifier.
Must be at least 1
characters long
Must be at most 150
characters long
EOC selection:
• labor
• material
• subcontract
• ODC
EU min. (dollars) work remaining.
EU most likely (dollars) work remaining.
EU max. (dollars) work remaining.
WBS is time-dependent (Y or N) for one or more associated tasks.
Basis.
Add justification narrative if WBS EU distribution is not
triangular.
Not required if WBS EU distribution is triangular or
WBS is completed or closed.
Unique subproject identifier.
Must be at least
1
characters long
Must be at most
50
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor task EU data for each
DS04.task_ID.
Provide the contractor schedule EU data.
Must contain a
minimum of 1
items
This object represents a forward pricing record for a project
No Additional PropertiesSchedule type selection:
• BL = baseline
• FC = forecast
Unique task identifier.
Must be at least 1
characters long
Must be at most 50
characters long
EU min. (work days) remaining.
EU most likely (work days) work remaining.
EU max. (work days) work remaining.
Basis.
Add justification narrative if activity is incomplete and
task EU distribution is not triangular.
Unique subproject identifier.
Must be at least
1
characters long
Must be at most
50
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor IMS tool standard work week
calendar data for the entire span of the project (not the contract).
Each weekday is
limited to 3 shifts (A, B, and C) for breaks in between shifts, starting with shift A, half
hour increments, and no overlaps.
If more than 3 shifts, 3rd shift should be stretched
to the last shift.
There should be alignment between the BL and FC IMSs.
Must contain a
minimum of 1
items
This item represents a calendar object assigned to a project, activity or a resource.
No Additional PropertiesUnique calendar name.
Must be at least
1
characters long
Must be at most
1000
characters long
Hours per day.
Standard work week shift_A_start time, Monday.
Standard work week shift_A_stop time, Monday.
Standard work week shift_B_start time, Monday.
Standard work week shift_B_stop time, Monday.
Standard work week shift_C_start time, Monday.
Standard work week shift_C_stop time, Monday.
Standard work week shift_A_start time, Tuesday.
Standard work week shift_A_stop time, Tuesday.
Standard work week shift_B_start time, Tuesday.
Standard work week shift_B_stop time, Tuesday.
Standard work week shift_C_start time, Tuesday.
Standard work week shift_C_stop time, Tuesday.
Standard work week shift_A_start time, Wednesday.
Standard work week shift_A_stop time, Wednesday.
Standard work week shift_B_start time, Wednesday.
Standard work week shift_B_stop time, Wednesday.
Standard work week shift_C_start time, Wednesday.
Standard work week shift_C_stop time, Wednesday.
Standard work week shift_A_start time, Thursday.
Standard work week shift_A_stop time, Thursday.
Standard work week shift_B_start time, Thursday.
Standard work week shift_B_stop time, Thursday.
Standard work week shift_C_start time, Thursday.
Standard work week shift_C_stop time, Thursday.
Standard work week shift_A_start time, Friday.
Standard work week shift_A_stop time, Friday.
Standard work week shift_B_start time, Friday.
Standard work week shift_B_stop time, Friday.
Standard work week shift_C_start time, Friday.
Standard work week shift_C_stop time, Friday.
Standard work week shift_A_start time, Saturday.
Standard work week shift_A_stop time, Saturday.
Standard work week shift_B_start time, Saturday.
Standard work week shift_B_stop time, Saturday.
Standard work week shift_C_start time, Saturday.
Standard work week shift_C_stop time, Saturday.
Standard work week shift_A_start time, Sunday.
Standard work week shift_A_stop time, Sunday.
Standard work week shift_B_start time, Sunday.
Standard work week shift_B_stop time, Sunday.
Standard work week shift_C_start time, Sunday.
Standard work week shift_C_stop time, Sunday.
Unique subproject identifier.
Must be at least
1
characters long
Must be at most
50
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor IMS tool calendar exception
data for the entire span of the project (not the contract).
Exception day is limited to
3 shifts (A, B, and C) for breaks in between shifts, starting with shift A, half hour
increments, and no overlaps.
If more than 3 shifts, 3rd shift should be stretched to the
last shift.
There should be alignment between the BL and FC IMSs.
This item represents an exception such as a holiday, associated with a DS19.calendar_name.
No Additional PropertiesCalendar name.
Must be at least
1
characters long
Must be at most
50
characters long
Date of exception.
Exception is a work day (Y or N).
If Y then all day is exception
and shift times do not need to be provided.
If N then provide
shift times.
Exception shift_A_start time.
Exception shift_A_stop time.
Exception shift_B_start time.
Exception shift_B_stop time.
Exception shift_C_start time.
Exception shift_C_stop time.
Unique subproject identifier.
Must be at least
1
characters long
Must be at most
50
characters long
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor EVMS cost tool resource
rates.
Provide the contractor EVMS cost tool resource rates by WP WBS level, resource
identifier, and applicable FYs.
The data may be UCNI.
Must contain a
minimum of 1
items
This object represents a rate record for a project
No Additional PropertiesResource identifier.
Must be at least 1
characters long
Must be at most 50
characters long
EOC selection aligned with DS03.EOC:
• labor
• material
•
subcontract
• ODC
Burden identifier (or overhead key) from accounting system, used to calculate indirect rate.
Must be at least 1
characters long
Must be at most 50
characters long
Rate type:
• D = direct rate
• I = indirect rate
Start date for which the rate is applicable.
Rate (dollars).
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.
This data set should be populated with the project's contractor financial tool calendar for the entire span of the project (not the contract).
Must contain a
minimum of 1
items
This object represents a contractor financial tool calendar
No Additional PropertiesUnique calendar name.
Must be at least
1
characters long
Must be at most
1000
characters long
Time-phased period end dates.
The data should align with the
contractor data-as-of date and the CPP_status_date.
The delta
between sequential dates should be a month.
There should be no
more than 12 period dates in a fiscal year.
Period identifier.
The data is >0, starting with 1 and
increments by 1.
Value must be greater or equal to
1
and lesser or equal to 600
For use only for debugging and testing with the PARS support team.
This field should be omitted in production data.
The field
should consist of a comma separated list of unique DIQ identifiers
that this row of data is expected to trigger.